SAP S/4HANA Portfolio and Project Management C_S4PPM_2021 Real Questions

  Edina  08-24-2023

If you are looking to excel in the C_S4PPM_2021 SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management exam, the latest SAP S/4HANA Portfolio and Project Management C_S4PPM_2021 Real Questions from PassQuestion are the perfect tool to aid you in your preparation. These comprehensive C_S4PPM_2021 exam questions cover all the exam objectives, including both theoretical and practical aspects, and provide a clear understanding of the exam structure. By using PassQuestion SAP S/4HANA Portfolio and Project Management C_S4PPM_2021 Real Questions, you can be confident in your ability to perform well in the exam and achieve your desired results.

C_S4PPM_2021 Exam Description - SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management

The "SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management" certification exam validates that the candidate possesses the fundamental and core knowledge required of the SAP S/4HANA PPM Implementation Consultant profile. This certification proves that the candidate has an overall understanding and inā€depth technical skills to participate as a member of a project team in a mentored role. This certification exam is recommended as an entry level qualification. This certification exam is relevant for SAP S/4HANA Cloud, private edition and SAP S/4HANA on-premise. The certificate issued for passing this exam will be valid for 5 years.

Exam Information

Exam Code: C_S4PPM_2021
Exam Name: SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management
Exam:80 questions
Cut Score:63%
Duration:180 mins
Languages:English

Topic Areas

Portfolio Definition > 12%
Project Definition > 12%
Financial and Capacity Planning > 12%
Integration and Shared Components > 12%
Project and Resource Planning 8% - 12%
Resource Management 8% - 12%
Questionnaires Scoring and Analytics 8% - 12%

View Online SAP S/4HANA Portfolio and Project Management C_S4PPM_2021 Free Questions

1.How can an existing project management project be integrated with SAP controlling? NOTE: There are 2 correct answers to this question.
A. Assign the project definition to an existing PS project definition manually
B. Transfer the project structure element to project system (PS)
C. Transfer the project structure element internal orders
D. Assign the project roles to an existing internal order manually
Answer: A,D

2.Which of the following can be viewed in the item dashboard? NOTE: There are 3 correct answers to this question.
A. Standard fields
B. Documents
C. Custom fields
D. authorizations
E. metrics
Answer: A,C,E

3.Which of the following object help to support automatic creation between portfolio and project management (PPM) and project system (PS)? NOTE: There are 2 correct answers to this question
A. PS profile
B. PS network
C. PS standard project
D. PS operative project
Answer: A,D

4.Your client wants to add additional checklist items to a project that has already began.
They want to control the items separately as unplanned.
Which setting must you make in customizing?
A. Create a checklist type and assign a new status Unplanned
B. Create a checklist item type and set the issue item indicator
C. Create a checklist item type and assign to the project type
D. Create a checklist type and set the issue list indicator
Answer: D

5.Which of the following can you use to create multiple portfolio items simultaneously?
A. Item template
B. Primavera import
C. Microsoft Excel import
D. Microsoft project import
Answer: A

6.Which of the following are basic parts of SAP innovation management? NOTE: There are 2 correct answers to this question.
A. Mobile web app
B. Idea community
C. Innovation office
D. Portfolio Review
E. Opportunity overview
Answer: A,B,C

7.You want to use a customer-specific status for items.
How do you configure the status in customizing?
A. Create a business add-in (BAdi) for customer-specific status management Activate the BAdi for the portfolio item type
B. Create a status profile for the portfolio item objet type Create the status within the status profile Assign the status profile to a portfolio item type 
C. Create the status Assign the status to a portfolio item type Specify the status transitions with respect the portfolio item type
D. Create the status and status transition within the portfolio type Assign the portfolio item type to the portfolio type
Answer: C

8.The probability technical success filed is enabled for questionnaires. You have defined a questionnaire for portfolio items In customizing. When you want to fill out the questionnaire for the probability technical success filed an error message is displayed.
What is the reason for the error message?
A. The field service configuration of the item is missing
B. The master switch for the interface settings for questionnaires it turned off
C. The probability technical success field is configured as read only in the field control
D. The field service configuration of the parent bucket of the item is missing
Answer: D

Leave And reply: