Looking for C_TS412_1909 real questions of SAP Certified Application Associate - SAP S/4HANA Project Systems exasm? PassQuestion offers the latest SAP S/4HANA Project Systems C_TS412_1909 Questions and Answers that will help you in passing the exam in the first attempt with the desired results. Our C_TS412_1909 Questions and Answers focus on each topic of the exams and these will help you in the best way to clear all of your doubts about your desired certification exam. After using our SAP S/4HANA Project Systems C_TS412_1909 Questions and Answers, you will be able to take the certification exam more confidently and this will help you in paving the path to the success in the exam.

C_TS412_1909 Exam Description - SAP Certified Application Associate - SAP S/4HANA Project Systems

The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.

Exam Details

Exam Code: C_TS412_1909
Exam Name: SAP Certified Application Associate - SAP S/4HANA Project Systems
Exam: 80 questions
Cut Score: 51%
Duration: 180 mins
Languages: English, Chinese

Topic Areas

Project Structures> 12%
Material> 12%
Resources> 12%
Dates> 12%
Cost and Budgets> 12%
Revenues and Payments> 12%
Reporting< 8%

View Online SAP S/4HANA Project Systems C_TS412_1909 Free Questions

You plan double the work on each internal activity for multiple project. What do you recommend?
A.Use mass change (CNMASS) in the project system.
B.Double the work of each internal activity, one after another, in the project Builder.
C.Double the capacity in the work center.
D.Use mass change within the project Builder (CJ20N).
Answer : A

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
A.A bill of material with sales views
B.A material master with sales views
C.Assignment between material and standard network
D.Standard network with activities
E.A production order
Answer : B, C, D

A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?
A.Settle the WBS element to the highest billing element before you do the result analysis.
B.Split the project intdifferent project according to each company code.
C.Change the project structure so that it correspond better to the company's organization structure.
D.Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.
Answer : C

You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?
A.The maintenance orders must be assigned to WBS element.
B.The maintenance order s must be assigned to the same budget profile as the project definition.
C.The maintenance orders must be assigned as sub-networks.
D.The maintenance orders must be assigned to the same plant as the network.
Answer : D

How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
A.Immediately, by saving the project
B.Automatically, using the requirement date and the replenishment lead time
C.Using a standard milestone activity
D.When releasing a network or an activity
Answer : B, D

A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
A.Settlement rules
B.Costing Sheet
C.Investment profile.
D.Results analysis key
Answer : A